GREATHOUSE APRIL 2024 UPDATE
Soon the Greathouse will begin the summer projects. Here are some of them. We
will keep you updated as the summer progresses.
MAY – 2nd week: Concrete repairs to begin in the A & C buildings
Mobilization of B Building Elevator Renovation
MAY – 3rd week: Concrete repairs to begin in the B building (appr 3 weeks)
Removal of decorative shutters at the B building
Start of B Building Elevator Renovation ( Appx 4 weeks)
JUNE – 1st week: Start of D Building Fire Alarm Upgrades
JUNE – 2nd week: Mobilization of D Building Elevator Renovation
Start of East Pool Resurfacing ( Appx 2 weeks)
JUNE – 3rd week: Start of D Building Elevator Renovation ( Appx 4 weeks)
JULY – 1st week: Start Painting B Buildings & Garages ( Appr 4 weeks)
AUG – 2nd week: Mobilization of C Building Elevator Renovation
Start of C Building Elevator Renovation ( Appx 3 weeks)